Lead Times Update 26 Nov 2020

For new orders, due to extended lead times from our chip vendors/suppliers, we are experiencing delays for key components used in LM products which are impacting the normal production cycle.

Please rest assured we are continuously liaising with our suppliers to reduce any lead times where possible.


We will continue to post new lead times as we receive further updates.
Please contact our Sales Team for existing stock availability.

Please refer to the list below for current lead times for new orders as of today;


Lead Times for new orders in weeks

  • LM007 16
  • LM072 30
  • LM074 32
  • LM048 30
  • LM058 30
  • LM068 32
  • LM400 30
  • LM506 16
  • LM746 30
  • LM747 30
  • LM808 16
  • LM809 16
  • LM811 16
  • LM813 16
  • LM816 16
  • LM817 16
  • LM822 16
  • LM823 16
  • LM832 16
  • LM842 16
  • LM843 16
  • LM910 16
  • LM930 30
  • LM931 30
  • LM961 32
  • LM1010 20